Emergency fiber work at Nebraska
Scheduled Maintenance Report for OSG Consortium
Postmortem

Maintenance was complete. Failover to backup fiber worked and there was no underlying outage observed.

Posted Jan 09, 2021 - 20:02 UTC

Completed
The scheduled maintenance has been completed.
Posted Jan 09, 2021 - 20:00 UTC
In progress
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Jan 09, 2021 - 16:01 UTC
Update
We will be undergoing scheduled maintenance during this time.
Posted Jan 09, 2021 - 14:57 UTC
Scheduled
UNL has some emergency fiber work happening tomorrow (Jan 9th) between 10am and 2pm Central time. This will likely make UNL’s Internet2 connections hiccup briefly multiple times during that window. There is a backup path to I2, and in the past the impact has been minimal for similar maintenance. This is purely a heads up in case folks notice anything tomorrow.
Posted Jan 08, 2021 - 16:10 UTC
This scheduled maintenance affected: Software Repositories (Yum Repos), Open Science Data Federation (StashCache Redirector, CVMFS Synchronization), and Accounting (GRACC Backend).